1997 UBC Earthquake Design

Base Shear Terms In this section, the various terms of the static base shear equation are examined in more detail. • Z : seismic zone facto...

Base Shear Terms

In this section, the various terms of the static base shear equation are examined in more detail.

• Z : seismic zone factor.


  • Effective peak ground accelerations with 10% probability of being exceeded in 50 yrs.
  • Given as a percentage of acceleration due to gravity.
  • For example, consider zone 4, where Z = 0.4g horizontal ground acceleration is predicted at 0.4g at bedrock.
  • Doesn't account for building dynamic properties or local soil conditions.
  • '97 UBC Figure 16.2? seismic zone map.
  • Table 16.1? Z values as given below:

Zone Z

0 0
1 0.075
2A 0.15
2B 0.20
3 0.30
4 0.40

• I : importance factor.


  • Classifying buildings according to use and importance.
  • Essential facilities, hazardous facilities, special occupancy structures, standard occupancy structures, miscellaneous structures.
  • Essential facilities mean that the building must remain functioning in a catastrophe.
  • Essential facilities include: hospitals, communication centers, fire and police stations.
  • Design for greater safety.
  • '97 UBC Table 16-K.
  • I = 1.25 for essential and hazardous facilities.
  • I = 1.0 all others.

•T : building's fundamental period of vibration.

Fundamental period of vibration is the length of time, in seconds, it takes a structure to move through one complete cycle of free vibration in the first mode.


There are two methods to estimate T:


  • Method A:




  • Method B: (an iterative approach not generally used in regular structures)



Using Method A, the fundamental period of vibrations for masonry buildings is estimated at:

Height (ft) Period (seconds)

20 0.19
40 0.32
60 0.43
120 0.73
160 0.90





  • Ca and Cv : seismic dynamic response spectrum values.
  • Accounts for how the building and soil can amplify the basic ground acceleration or velocity.
  • Ca and Cv are determined from respectively '97 UBC tables 16-Q and 16-R as a function of Z, underlying soil conditions, and proximity to a fault.
  • Using method A,
  • Soil profile type:
  • The soil layers beneath a structure effects the way that structure responds to the earthquake motion.



When the period of vibration of the building is close to the period of vibration of the underlying soil, the bedrock motion is amplified. The building experiences larger motions than that predicted by Z alone. The following are generalizations about building response as a function of building flexibility and underlying soil stiffness.

  • Building Description Soil Description Induced Seismic Force
  • Flexible (Large T's) Soft (big S) Higher
  • Flexible Stiff Lower
  • Stiff Soft Higher
  • Flexible Stiff Lower


  • The soil profile types are:
  • Description Type
  • Hard Rock SA
  • Rock SB
  • Very dense soil and soft rock SC
  • Stiff soil SD
  • Soft soil SE
  • See '97 UBC 1629.3.1 SF


Specific details about each type can be found in '97 UBC Table 16-J and '97 UBC 1629.3.1.


  • In the absence of a Geo-technical site investigation, use SD. This is in accordance with '97 UBC 1629.3
  • Do not confuse this requirement with the one stated in '97 UBC 1630.2.3.2 which applies ONLY when using the simplified design base shear procedures of '97 UBC 1630.2.3. This web site is NOT using these simplified procedures, but is using 1630.2.1.

  • R = response modification factor.
  • A judgement factor that accounts for building ductility, damping, and over-strength.
  • Ductility = ability to deform in the inelastic range prior to fracture:


Damping = resistance to motion provided by internal material friction.


  • Over-strength : the extra or reserve strength in the structural system. It comes from the practice of designing every member in a group according to the forces in the most critical member of that group.
  • Structural systems with larger R = better seismic performance.
  • In '97 UBC Table 16-N, R range from 2.8 (light steel frame bearing walls with tension bracing) to 8.5 (special SMRFS of steel or concrete and some dual systems).
  • For bearing wall systems where the wall elements resist both lateral and vertical loads:
  • Wood shear panel buildings with 3 or less stories: R = 5.5
  • Masonry shear walls: R = 4.5.
  • Nv and Na : near source factors that are applicable in only seismic zone 4. They account for the very large ground accelerations that occur near the seismic source (the fault).
  • Nv is generally used with Cv for structures located < 9.3 miles (15km) from the fault.
  • Nv is found in '97 UBC Table 16-T
  • Na is used with Ca for structures located < 6.2 miles (10 km) from the fault.
  • Na is found in '97 UBC Table 16-S.
  • Both Na and Nv are based upon the type of seismic source, A-C. This source type, and location of fault, must be established using approved geotechnical data like a current USGS survey.





Name

• compression couplers,1,• tension couplers,1,1997 UBC,1,56 days Concrete test,1,ADDICRETE,1,additives,1,administer computer networks,1,admixtures,1,Advises Subcontractors,1,alignment of the shafts,1,Allowable Stress Design,1,Anchor Bolts,1,Annual depreciation expense,1,approval of drawings,1,ASCE7,1,ASD,1,Assist in Quantity,1,Assist the Project Manager,1,Authority to Delegate,1,AutoCAD,2,AutoCAD to Etabs,1,bagger,1,bars,1,bars in a bundle,1,BASE ISOLATED DAMAGE,1,base plates,1,basement wall,1,Basic soil properties,1,basic wind speed,1,Beams Inspection Checklist,1,Bearing capacity,1,bell pile bottom,1,bent bars,1,Bitomeneous,1,Blockwork,1,Bowels,1,breaching spillway,1,BS 8007:1987,1,BS5400,1,BS6399,1,BS8007,1,BS8110-1997,1,building materials,1,buildings height,1,CALCULATION OF CRACK WIDTH,1,Canary Island Dates,1,cantilever footing,1,Carbon Equivalent,1,carbon test,1,cast in-situ,1,cast-in-place anchors,1,cast-in-place concrete pile,1,Cause-and-effect diagram,1,Chairs,1,Check sheets,1,Chemical Admixtures,1,Chute spillway,1,CIRIA,2,CIRIA Report 136,1,civil engineering,1,civil structures,1,Coal ash,1,collars,1,Collision Load,1,columns,3,columns and walls,1,Combination of combinations,1,combinations in Etabs,1,Company's Health,1,Compliant Towers platforms,1,compression test,1,compressive strength,1,concrete,4,concrete block buildings,1,CONCRETE IN HOT WEATHER,1,CONCRETE MOMENT FRAME,1,concrete pile,1,Concrete Rebound Hammer,1,Concrete Shrinkage,1,Concrete Slump Test,1,concrete walls,1,Construction and Stressing,1,Construction companies in Dubai,1,construction drawings,1,construction industry,1,Construction joints,1,Construction Manual,1,continuous external restraint,1,continuous slabs,1,contract planresponsibilities of QA/QC,1,Contracts Manager,1,cooling pipe system,1,Corner reinforcement,1,Cost Plus Award Fee,1,Cost-reimbursable,1,COUPLED SHEAR WALL,1,Couplers,1,couplers in columns,1,CP3,1,CRACK WIDTH,1,Creep,1,CURING,1,day to day work progress,1,Dead load and Self-weight,1,Deck,1,Deflection,1,Deflection discussion,1,Deflection in Prestressed,1,deformed bars,1,Demolition,1,design drawings,1,Design Requirements,1,designing a tall building,1,Designs projects,1,detailed review,1,detailing and implementation,1,Development length,1,different codes in one structure,1,Differential elastic shortening,1,dimensions,1,DIRECT TENSION,1,Draftsman responsibilities,1,drawings and specifications,1,Drift Limitations,1,Drop beams,1,dust loads,1,dust on roof,1,Dynamic Pile Head,1,dynamic wind pressure,1,Early age Crackwidth,1,early strength cement,1,Earth pressure,1,Earthquake Design,1,earthquakes,1,EBT adhesive sealant,1,Elastic Shortening,1,electrical and manual,1,elevator requirement,1,Elevators,1,Encasement of pipes,1,end plate connection,1,Energy dissipater,1,engineering design,1,Environmental procedures,1,epoxy compound,1,Epoxy grout,1,equipment performance records,1,Error and warning free model,1,Errors in Etabs,1,establishment of construction,1,Estimating Flow Standard,1,Etabs,2,Etabs Design,1,ETABS to ROBOT,1,excavation,1,Excavation slopes,1,external concrete surfaces,1,Finishing of slip-forms,1,Fire,1,Firm Fixed Price,1,Fixed platforms,1,Fixed Price Incentive Fee,1,Fixed Price with Economic,1,Flexible Joints,1,Flexible pipes,1,floors,1,Flow charts,1,Fly ash,1,Foundation analysis,2,Foundations,2,framed openings,1,Free over fall spillway,1,FRP,1,FRP advantages,1,FRP disadvantages,1,FRP technology,1,full length bar,1,General Notes,1,Geophone sensor,1,Hammer Schmidt Type,1,HDP,1,Health and Safety procedures,1,helical piering,1,helical piles,1,High Early Strength Portland Cement,1,High quality additives,1,high rise / tower,1,highly effective,1,Histograms,1,hooked bars,1,Horizontal steel,1,Human Comfort,1,hydraulic,1,hydraulic jump,1,Hydraulic resistance,1,Hydro technical tunnels,1,IBC/ASCE,1,immediate reaction,1,importance of Plasticizers,1,Importing,1,IMS,1,Inspection Checklist,6,INSTRUMENT CALIBRATION,1,inter-story drift,1,interest payments,1,IT engineer responsibilities,1,Jack-up Platforms,1,Jacking Systems,1,Japanese code for escalators,1,Kicker,1,largest man-made machine,1,largest man-made machine on earth,1,largest oil platform,1,lateral forces,1,lateral loads,1,LFD,1,lifting hooks,1,Load Factor Design,1,load resisting elements,1,load-bearing wall,1,Loading,1,Loads and Resistances,1,LRFD,1,Maintain contract database,1,Maintains close scrutiny,1,maintenance cost,1,Makes recommendations,1,manage,1,manufacturer,1,manufacturing process,1,Maximum allowable slopes,1,maximum deflection,1,maximum difference,1,maximum pressure,1,maximum reinforcement,1,maximum temperature,1,Mechanical couplers,1,Mechanical damage,1,membrane floors,1,Metal sleeves swaged,1,Method of dissipation,1,METHOD OF TESTING,1,Method statement,2,Mineral Admixtures,1,minimize the seepage,1,minimizing the cost,1,minimum eccentricity moment,1,Minimum reinforcement,1,mixing concrete,1,modelling in Etabs,1,Monitors performance,1,monthly invoice,1,Monthly Safety Report,1,Most Useless Megaprojects in the World,1,multi-storey buildings,1,multistory buildings,1,Natural frequency,1,Necessity of tunnel lining,1,new structural systems,1,O&M,1,of concrete block buildings,1,office buildings,1,Office Tall Buildings,1,offshore platforms,1,oil platform,1,oil rigs,1,on beams from loaded slab can be achieved by defining the slab as a membrane,1,opening reinforcement,1,ordinary Portland cement,2,Other bars,1,Overlap,1,overlap locations,1,Oversee and review,1,palm trees weight,1,parallel threads,1,parapet,1,Perform data backups,1,Performance Bonds,1,Performs design drafting,1,physical properties,1,pile cap,1,Pile Dynamic Test,1,Pile Head Preparation,1,Pile Integrity Testing,1,Pile Shaft Overbreak,1,piles foundations,1,Pindos,1,Pipe Classifications,1,PLACING,1,Placing boom,1,Plan and prioritize work,1,Planning Engineer,1,plant and equipment,1,Plant and Equipment Engineer,1,plaster walls,1,Platform types,1,pneumatic,1,Post-Tensioning Grouting,1,Pour strip,1,precast panel,1,Prepares monthly report,1,Pressure Ratings,1,Prestressed Concrete,1,prevent uplift,1,principal load resisting,1,procedure of fixing,1,Project Coordinator,1,Project manager assignment,1,project schedule,1,project's compliance,1,Provides technical expertise,1,provisional Sum,2,PT slabs,2,pump,1,PVC,1,QA,1,QA/QC Engineer,1,QC,1,Quality,1,quotes,1,Quotes of Engineers,1,raft foundations,1,Raft Slab Inspection Checklist,1,reaction as an engineer,1,rebound hammer,1,recommended tests,1,Recorded experience,1,Reinforced concrete columns,1,reinforcement,1,Reinforcement at openings,1,reinforcing bars,2,reinforcing-steel,1,Residential Tall Buildings,1,RESISTING SYSTEMS DAMAGE,1,Retaining Wall Inspection Checklist,1,Retaining walls,1,retarder,1,Review contract documents,1,review contracts,1,review expiring contracts,1,Reviews accidents,1,reviews contract drafts,1,Reviews shop drawings,1,Reviews the terms and conditions,1,Rice husk ash,1,rigid foundation,1,Rigid pipes,1,Road layers,1,Robot Millennium,1,Rock Strata and Excavation,1,Roles and Responsibilities,8,Roller bucket,1,Rough Order of Magnitude,1,Rules of thumb,1,saddle beams,1,Safe 14,1,Safety Manager,1,sample letter,3,sand,1,SAP2000,1,Schmidt Hammer,1,Seismic,1,Seismic Design Principle,1,Seismic force,1,SEISMIC RESISTING SYSTEMS,1,seismic zone factor,1,Semi-structural welding,1,Semi-submersible Platforms,1,Senior Architect,1,Senior Contracts Engineer,1,Sequential Loading,1,Set work program,1,Seven Basic Quality Tools,1,shallow foundation,1,Shell,1,Ship-board Rigs platforms,1,shop drawings,1,shortening of columns,1,Shrinkage,1,Shrinkage and Temperature,1,Side channel spillway,1,simply supported,1,Site engineer responsibilities,1,site facilities,1,Site Investigation,1,SK Gosh,1,Ski-jump,1,slab assignment,1,slabs,2,Slabs Inspection Checklist,1,slings,1,slip forms,1,Slip-form,1,Slip-form construction,1,slip-forming,1,smooth finish,1,soffit slabs,1,Soil classification,1,Soil Sloping Systems,1,Soil Testing,1,speed of erection,1,Spring Force,1,standard size bolts,1,Static load,1,Static load multiplier,1,steel beam,1,Steel Columns,1,steel quantity,1,steel stress,1,Stiffness,1,stiffness and resistance,1,stilling basin,1,Strap footing,1,Strength and Stability,1,Stress on soil in etabs,1,Stressing sequence,1,Striking formworks,2,Strip footing,1,Strong Column,1,structural construction process,1,structural design spreadsheet,1,Structural Details,1,structural engineers,1,Structural Provisions,1,structural purposes pipes,1,strukts spreadsheets,1,Subcontract Agreement,1,Super-plasticizers,2,surfactants,1,Tack welding,1,Tall Building,1,tall buildings,1,taper-cut threads,1,Tdr Test Accuracy,1,Technical Engineer,1,technical submittals,1,test hammer,1,Test on Piles,1,Test specimens,1,TESTING,1,Thermal Expansion,1,threaded rods with nuts,1,time for completion,1,Top bars,1,torsion-load test,1,Total Shortening,1,tower cranes,1,Tower cranes installation,1,Transform AUTOCAD drawings,1,trough spillway,1,Trump Tower,1,Tunnel,1,tunnel lining,1,type of concrete,1,Types of contracts,1,types of foundation,1,Types of shallow foundation,1,Types of spillways,1,Types of waterproofing,1,Ultra Ever Dry,1,Uniform loads Safe 14,1,uniform thickness,1,Uplift Force,1,uplift test lateral-load test,1,vertical load resisting,1,Voided Biaxial Slabs,1,wall openings,1,walls,2,Warning,1,Water curing,1,Weak Beam Concept,1,Wedge locking sleeves,1,weekly and monthly program,1,weekly and monthly report,1,Welding of reinforcement,1,Welding procedures,1,What teachers never taught us,1,wind and seismic,1,Wind loads,1,Wind simulation,1,WOOD SHEAR WALL,1,workability,2,workshop drawings,1,Workshop repair,1,
ltr
item
Strukts: 1997 UBC Earthquake Design
1997 UBC Earthquake Design
https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEiF0q3sh8AOsU_69y9Fvh50vjcWEI6u5aW5wnS1purXwicStDYVYGBmWHD0YIANELlpBN_b4fFlJW0gtHECfuIQ2YuYPz-dI4qWTXiNL8DUgN4CJPRzKuHB0oMhiKX64tP11xLJZSc2IMI/s1600/7361b4ed62558e57f3769b48f19cd7.gif
https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEiF0q3sh8AOsU_69y9Fvh50vjcWEI6u5aW5wnS1purXwicStDYVYGBmWHD0YIANELlpBN_b4fFlJW0gtHECfuIQ2YuYPz-dI4qWTXiNL8DUgN4CJPRzKuHB0oMhiKX64tP11xLJZSc2IMI/s72-c/7361b4ed62558e57f3769b48f19cd7.gif
Strukts
https://www.strukts.com/2013/01/1997-ubc-earthquake-design_75.html
https://www.strukts.com/
https://www.strukts.com/
https://www.strukts.com/2013/01/1997-ubc-earthquake-design_75.html
true
7606260228666216043
UTF-8
Loaded All Posts Not found any posts VIEW ALL Readmore Reply Cancel reply Delete By Home PAGES POSTS View All RECOMMENDED FOR YOU LABEL ARCHIVE SEARCH ALL POSTS Not found any post match with your request Back Home Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sun Mon Tue Wed Thu Fri Sat January February March April May June July August September October November December Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec just now 1 minute ago $$1$$ minutes ago 1 hour ago $$1$$ hours ago Yesterday $$1$$ days ago $$1$$ weeks ago more than 5 weeks ago Followers Follow THIS PREMIUM CONTENT IS LOCKED STEP 1: Share to a social network STEP 2: Click the link on your social network Copy All Code Select All Code All codes were copied to your clipboard Can not copy the codes / texts, please press [CTRL]+[C] (or CMD+C with Mac) to copy