Changes in ACI318-11

The American Concrete Institute (ACI) has published Building Code Requirements for Structural Concrete (ACI 318-11) and Commentary (ACI ...



The American Concrete Institute (ACI) has published Building Code Requirements for Structural Concrete (ACI 318-11) and Commentary (ACI 318R-11) and it has been adopted by the 2012 International Building Code (IBC).

Although the changes from ACI 318-08 to ACI 318-11 are not as those between ACI 318-05 and ACI 318-08, some of the changes in the latest cycle are definitely significant.

Chapter 3 — Materials
ASTM A615 "Standard Specification for Deformed and Plain Carbon Steel Bars for Concrete Reinforcement" and ASTM A706 "Standard Specification for Low-Alloy Steel Deformed and Plain Bars for Concrete Reinforcement" have both added a Grade 80 reinforcement, having a minimum yield strength of 80,000 psi (550 MPa). However, the use of this reinforcement is not permitted by Section 21.1.5 in special moment frames and special structural walls.



Chapter 7 — Details of Reinforcement

  1. In new Section 7.10.5.4, rigorous detailing requirements for complete circular ties around longitudinal bars located around the perimeter of a circular column are given.

  2. New requirements have been added in Sections 7.12.3.2 through 7.12.3.5 concerning temperature and shrinkage reinforcement in post-tensioned slabs.

Chapter 9 — Strength and Serviceability Requirements
APPENDIX C — Alternative Load and Strength Reduction Factors


The strength design load combinations in Sections 9.2 and C.9.2 have been revised to be fully consistent with those of ASCE/SEI 7-10.

Chapter 11 — Shear and Torsion
In Section 11.7.4.2, the area of shear reinforcement parallel to the longitudinal axis of the beam is now required to be not less than 0.0025 bws2, rather than 0.0015 bws2, where bw is web width and s2 is center-to-center spacing of longitudinal shear reinforcement.

Chapter 18 — Prestressed Concrete

  1. The permissible stress of 0.82 fpy (fpy = specified yield strength of prestressing steel) but not greater than 0.74 fpu (fpu = specified tensile strength of prestressing steel) in prestressing steel immediately upon prestress transfer in Section 18.5.1 has been eliminated based upon practical experience with post-tensioned concrete members.

  2. The formulas for estimating friction loss in post-tensioning tendons have been eliminated from Section 18.6.2.1 as being text-book material.

Chapter 21 — Earthquake-Resistant Structures

  1. In Section 21.3.3 of ACI 318-08, the required shear strength of a column of an intermediate moment frame was permitted to be calculated as the maximum shear obtained from design load combinations that include E, with E assumed to be twice that prescribed by the general building code. In the new Section 21.3.3.2 of ACI 318-11, the multiplier of two has been increased to the overstrength factor, ?0= 3, of the intermediate moment frame.

  2. In ACI 318-08 Section 21.5.3.2, the spacing of hoops within the region of potential plastic hinging at each end of a special moment frame beam could not exceed the smallest of:

    1. d/4;

    2. eight times the diameter of the smallest longitudinal bars;

    3. 24 times the diameter of the hoop bars; and

    4. 12 inches. In ACI 318-11 Section 21.5.3.2,

Item (2) has been changed to six times the diameter of the smallest primary flexural reinforcing bars excluding longitudinal skin reinforcement required by Section 10.6.7. Item (3) has been deleted. Item (4) now is 6 inches. For deeper beams, this is a significant decrease in the spacing of confinement reinforcement in regions of potential plastic hinging.

3.  New Section 21.6.3.2 requires that in columns with circular hoops, the minimum number of longitudinal bars be six for effective confinement.

4.  Section 21.9.6.4(e), applicable to special shear walls with special boundary elements, has been expanded to: "Horizontal reinforcement in the wall web shall extend to within 6 in (150mm) of the end of the wall. Reinforcement shall be anchored to develop fy in tension using standard hooks or heads. Where the confined boundary element has sufficient length to develop the horizontal web reinforcement, and Avfy/s of the web reinforcement is not greater than Ashfyt/s of the boundary element transverse reinforcement parallel to the web reinforcement, it shall be permitted to terminate the web reinforcement without a standard hook or head." See Figure 1.




















Figure 1. Development of wall horizontal reinforcement in confined boundary element


5.  Door and window openings in shear walls often lead to narrow vertical wall segments, many of which have been defined as wall piers in the IBC and in the UBC before it. Wall pier provisions are now included in Section 21.9.8 of ACI 318-11. The dimensions defining wall piers are given in Section 2.2.

Shear failures of wall piers have been observed in previous earthquakes. The intent of Section 21.9.8 is to prescribe detailing that would result in flexural failure preceding shear failure in wall piers. The provisions apply to wall piers considered part of the seismic force-resisting system (SFRS). Wall piers considered not part of the SFRS need to be designed by Section 21.13.

Wall piers having (lw/bw) ? 2.5 behave essentially as columns. Section 21.9.8.1 requires them to be detailed like columns. Alternative requirements are provided for wall piers having (lw/bw) > 2.5.

Wall piers at the edge of a wall are addressed in Section 21.9.8.2. Under in-plane shear, inclined cracks can propagate into segments of the wall directly above and below the wall pier. Shear failure within the adjacent wall segments can occur unless sufficient reinforcement is provided in those segments (Figure R21.9.8).

An excellent new Table R21.9.1 in the Commentary effectively summarizes the new requirements.

APPENDIX D — Anchoring to Concrete
1) The onerous nature of seismic design imposed by ACI 318-08 Section D.3.3 on anchors in Seismic Design Category (SDC) C or higher is alleviated and the seismic design of anchors is made considerably more reasonable. Where the tension component of the strength-level earthquake force applied to the anchor or group of anchors is equal to or less than 20 percent of the total factored anchor tensile force, the seismic design requirements of Section D.3.3 to prevent a brittle tension failure of anchors simply do not apply any more (Section D.3.3.4.1). A similar provision concerning shear is included in Section D.3.3.5.1.

Where the seismic component of the total factored tension demand on an anchor or a group of anchors exceeds 20 percent, the following four options have been made available:

(a) Ensure failure of ductile steel anchor ahead of the brittle failure of concrete (Section D.3.3.4.3(a)). This now involves the new concept of a stretch length.

(b) Design anchor for the maximum tension force that can be transmitted by a ductile metal attachment after considering the overstrength and strain hardening of the attachment (D.3.3.4.3(b)).

(c) Design for the maximum tension force that can be transmitted by a non-yielding attachment (Section D.3.3.4.3(c)).

(d) Design for the maximum tension force obtained from design load combinations involving E, with multiplied by ?0 (Section D.3.3.4.3(d)).

For an anchor or a group of anchors subject to shear, three options similar to (b), (c), and (d) above have been made available. Unlike ACI 318-08, ductile anchor failure in shear is not an option anymore.

2) The maximum anchor diameter for which the provisions of Sections D.5.2 and D.6.2 can be applied to calculate the concrete breakout strength in tension and shear, respectively, has been increased from 2 inches to 4 inches (Section D.4.2.2). This expansion is based on the results of new tests using larger diameter anchors. However, a new Eq. D-34 has also been introduced for a lower-bound value of basic concrete breakout strength for a single anchor in shear, Vb, to account for the larger diameter anchors.

ACI 318-08 also imposed a 25-inch limitation on anchor embedment depth for the calculation of concrete breakout strength using the provisions of Appendix D. This limitation was effectively removed by Section 1908.1.10 of the 2009 IBC and is now gone from ACI 318-11.

3) An adhesive anchor is defined in Section D.1 as a post-installed anchor, inserted into hardened concrete with an anchor hole diameter not greater than 1.5 times the anchor diameter, that transfers loads to the concrete by bond between the anchor and the adhesive, and bond between the adhesive and the concrete. Failure modes and the corresponding nominal strengths for adhesive anchors are defined, along with requirements for testing and evaluation of adhesive anchors for use in cracked concrete or subject to sustained loads. Failure modes postulated for other anchors apply to adhesive anchors as well, except that the calculation of strength governed by anchor pullout is replaced by the evaluation of adhesive bond strength in accordance with Section D.5.5. The provisions for adhesive anchors include criteria for overhead anchors, seismic design requirements, installation and inspection requirements, and certification of adhesive anchor installers. Separately, a certification program has been established.


Name

• compression couplers,1,• tension couplers,1,1997 UBC,1,56 days Concrete test,1,ADDICRETE,1,additives,1,administer computer networks,1,admixtures,1,Advises Subcontractors,1,alignment of the shafts,1,Allowable Stress Design,1,Anchor Bolts,1,Annual depreciation expense,1,approval of drawings,1,ASCE7,1,ASD,1,Assist in Quantity,1,Assist the Project Manager,1,Authority to Delegate,1,AutoCAD,2,AutoCAD to Etabs,1,bagger,1,bars,1,bars in a bundle,1,BASE ISOLATED DAMAGE,1,base plates,1,basement wall,1,Basic soil properties,1,basic wind speed,1,Beams Inspection Checklist,1,Bearing capacity,1,bell pile bottom,1,bent bars,1,Bitomeneous,1,Blockwork,1,Bowels,1,breaching spillway,1,BS 8007:1987,1,BS5400,1,BS6399,1,BS8007,1,BS8110-1997,1,building materials,1,buildings height,1,CALCULATION OF CRACK WIDTH,1,Canary Island Dates,1,cantilever footing,1,Carbon Equivalent,1,carbon test,1,cast in-situ,1,cast-in-place anchors,1,cast-in-place concrete pile,1,Cause-and-effect diagram,1,Chairs,1,Check sheets,1,Chemical Admixtures,1,Chute spillway,1,CIRIA,2,CIRIA Report 136,1,civil engineering,1,civil structures,1,Coal ash,1,collars,1,Collision Load,1,columns,3,columns and walls,1,Combination of combinations,1,combinations in Etabs,1,Company's Health,1,Compliant Towers platforms,1,compression test,1,compressive strength,1,concrete,4,concrete block buildings,1,CONCRETE IN HOT WEATHER,1,CONCRETE MOMENT FRAME,1,concrete pile,1,Concrete Rebound Hammer,1,Concrete Shrinkage,1,Concrete Slump Test,1,concrete walls,1,Construction and Stressing,1,Construction companies in Dubai,1,construction drawings,1,construction industry,1,Construction joints,1,Construction Manual,1,continuous external restraint,1,continuous slabs,1,contract planresponsibilities of QA/QC,1,Contracts Manager,1,cooling pipe system,1,Corner reinforcement,1,Cost Plus Award Fee,1,Cost-reimbursable,1,COUPLED SHEAR WALL,1,Couplers,1,couplers in columns,1,CP3,1,CRACK WIDTH,1,Creep,1,CURING,1,day to day work progress,1,Dead load and Self-weight,1,Deck,1,Deflection,1,Deflection discussion,1,Deflection in Prestressed,1,deformed bars,1,Demolition,1,design drawings,1,Design Requirements,1,designing a tall building,1,Designs projects,1,detailed review,1,detailing and implementation,1,Development length,1,different codes in one structure,1,Differential elastic shortening,1,dimensions,1,DIRECT TENSION,1,Draftsman responsibilities,1,drawings and specifications,1,Drift Limitations,1,Drop beams,1,dust loads,1,dust on roof,1,Dynamic Pile Head,1,dynamic wind pressure,1,Early age Crackwidth,1,early strength cement,1,Earth pressure,1,Earthquake Design,1,earthquakes,1,EBT adhesive sealant,1,Elastic Shortening,1,electrical and manual,1,elevator requirement,1,Elevators,1,Encasement of pipes,1,end plate connection,1,Energy dissipater,1,engineering design,1,Environmental procedures,1,epoxy compound,1,Epoxy grout,1,equipment performance records,1,Error and warning free model,1,Errors in Etabs,1,establishment of construction,1,Estimating Flow Standard,1,Etabs,2,Etabs Design,1,ETABS to ROBOT,1,excavation,1,Excavation slopes,1,external concrete surfaces,1,Finishing of slip-forms,1,Fire,1,Firm Fixed Price,1,Fixed platforms,1,Fixed Price Incentive Fee,1,Fixed Price with Economic,1,Flexible Joints,1,Flexible pipes,1,floors,1,Flow charts,1,Fly ash,1,Foundation analysis,2,Foundations,2,framed openings,1,Free over fall spillway,1,FRP,1,FRP advantages,1,FRP disadvantages,1,FRP technology,1,full length bar,1,General Notes,1,Geophone sensor,1,Hammer Schmidt Type,1,HDP,1,Health and Safety procedures,1,helical piering,1,helical piles,1,High Early Strength Portland Cement,1,High quality additives,1,high rise / tower,1,highly effective,1,Histograms,1,hooked bars,1,Horizontal steel,1,Human Comfort,1,hydraulic,1,hydraulic jump,1,Hydraulic resistance,1,Hydro technical tunnels,1,IBC/ASCE,1,immediate reaction,1,importance of Plasticizers,1,Importing,1,IMS,1,Inspection Checklist,6,INSTRUMENT CALIBRATION,1,inter-story drift,1,interest payments,1,IT engineer responsibilities,1,Jack-up Platforms,1,Jacking Systems,1,Japanese code for escalators,1,Kicker,1,largest man-made machine,1,largest man-made machine on earth,1,largest oil platform,1,lateral forces,1,lateral loads,1,LFD,1,lifting hooks,1,Load Factor Design,1,load resisting elements,1,load-bearing wall,1,Loading,1,Loads and Resistances,1,LRFD,1,Maintain contract database,1,Maintains close scrutiny,1,maintenance cost,1,Makes recommendations,1,manage,1,manufacturer,1,manufacturing process,1,Maximum allowable slopes,1,maximum deflection,1,maximum difference,1,maximum pressure,1,maximum reinforcement,1,maximum temperature,1,Mechanical couplers,1,Mechanical damage,1,membrane floors,1,Metal sleeves swaged,1,Method of dissipation,1,METHOD OF TESTING,1,Method statement,2,Mineral Admixtures,1,minimize the seepage,1,minimizing the cost,1,minimum eccentricity moment,1,Minimum reinforcement,1,mixing concrete,1,modelling in Etabs,1,Monitors performance,1,monthly invoice,1,Monthly Safety Report,1,Most Useless Megaprojects in the World,1,multi-storey buildings,1,multistory buildings,1,Natural frequency,1,Necessity of tunnel lining,1,new structural systems,1,O&M,1,of concrete block buildings,1,office buildings,1,Office Tall Buildings,1,offshore platforms,1,oil platform,1,oil rigs,1,on beams from loaded slab can be achieved by defining the slab as a membrane,1,opening reinforcement,1,ordinary Portland cement,2,Other bars,1,Overlap,1,overlap locations,1,Oversee and review,1,palm trees weight,1,parallel threads,1,parapet,1,Perform data backups,1,Performance Bonds,1,Performs design drafting,1,physical properties,1,pile cap,1,Pile Dynamic Test,1,Pile Head Preparation,1,Pile Integrity Testing,1,Pile Shaft Overbreak,1,piles foundations,1,Pindos,1,Pipe Classifications,1,PLACING,1,Placing boom,1,Plan and prioritize work,1,Planning Engineer,1,plant and equipment,1,Plant and Equipment Engineer,1,plaster walls,1,Platform types,1,pneumatic,1,Post-Tensioning Grouting,1,Pour strip,1,precast panel,1,Prepares monthly report,1,Pressure Ratings,1,Prestressed Concrete,1,prevent uplift,1,principal load resisting,1,procedure of fixing,1,Project Coordinator,1,Project manager assignment,1,project schedule,1,project's compliance,1,Provides technical expertise,1,provisional Sum,2,PT slabs,2,pump,1,PVC,1,QA,1,QA/QC Engineer,1,QC,1,Quality,1,quotes,1,Quotes of Engineers,1,raft foundations,1,Raft Slab Inspection Checklist,1,reaction as an engineer,1,rebound hammer,1,recommended tests,1,Recorded experience,1,Reinforced concrete columns,1,reinforcement,1,Reinforcement at openings,1,reinforcing bars,2,reinforcing-steel,1,Residential Tall Buildings,1,RESISTING SYSTEMS DAMAGE,1,Retaining Wall Inspection Checklist,1,Retaining walls,1,retarder,1,Review contract documents,1,review contracts,1,review expiring contracts,1,Reviews accidents,1,reviews contract drafts,1,Reviews shop drawings,1,Reviews the terms and conditions,1,Rice husk ash,1,rigid foundation,1,Rigid pipes,1,Road layers,1,Robot Millennium,1,Rock Strata and Excavation,1,Roles and Responsibilities,8,Roller bucket,1,Rough Order of Magnitude,1,Rules of thumb,1,saddle beams,1,Safe 14,1,Safety Manager,1,sample letter,3,sand,1,SAP2000,1,Schmidt Hammer,1,Seismic,1,Seismic Design Principle,1,Seismic force,1,SEISMIC RESISTING SYSTEMS,1,seismic zone factor,1,Semi-structural welding,1,Semi-submersible Platforms,1,Senior Architect,1,Senior Contracts Engineer,1,Sequential Loading,1,Set work program,1,Seven Basic Quality Tools,1,shallow foundation,1,Shell,1,Ship-board Rigs platforms,1,shop drawings,1,shortening of columns,1,Shrinkage,1,Shrinkage and Temperature,1,Side channel spillway,1,simply supported,1,Site engineer responsibilities,1,site facilities,1,Site Investigation,1,SK Gosh,1,Ski-jump,1,slab assignment,1,slabs,2,Slabs Inspection Checklist,1,slings,1,slip forms,1,Slip-form,1,Slip-form construction,1,slip-forming,1,smooth finish,1,soffit slabs,1,Soil classification,1,Soil Sloping Systems,1,Soil Testing,1,speed of erection,1,Spring Force,1,standard size bolts,1,Static load,1,Static load multiplier,1,steel beam,1,Steel Columns,1,steel quantity,1,steel stress,1,Stiffness,1,stiffness and resistance,1,stilling basin,1,Strap footing,1,Strength and Stability,1,Stress on soil in etabs,1,Stressing sequence,1,Striking formworks,2,Strip footing,1,Strong Column,1,structural construction process,1,structural design spreadsheet,1,Structural Details,1,structural engineers,1,Structural Provisions,1,structural purposes pipes,1,strukts spreadsheets,1,Subcontract Agreement,1,Super-plasticizers,2,surfactants,1,Tack welding,1,Tall Building,1,tall buildings,1,taper-cut threads,1,Tdr Test Accuracy,1,Technical Engineer,1,technical submittals,1,test hammer,1,Test on Piles,1,Test specimens,1,TESTING,1,Thermal Expansion,1,threaded rods with nuts,1,time for completion,1,Top bars,1,torsion-load test,1,Total Shortening,1,tower cranes,1,Tower cranes installation,1,Transform AUTOCAD drawings,1,trough spillway,1,Trump Tower,1,Tunnel,1,tunnel lining,1,type of concrete,1,Types of contracts,1,types of foundation,1,Types of shallow foundation,1,Types of spillways,1,Types of waterproofing,1,Ultra Ever Dry,1,Uniform loads Safe 14,1,uniform thickness,1,Uplift Force,1,uplift test lateral-load test,1,vertical load resisting,1,Voided Biaxial Slabs,1,wall openings,1,walls,2,Warning,1,Water curing,1,Weak Beam Concept,1,Wedge locking sleeves,1,weekly and monthly program,1,weekly and monthly report,1,Welding of reinforcement,1,Welding procedures,1,What teachers never taught us,1,wind and seismic,1,Wind loads,1,Wind simulation,1,WOOD SHEAR WALL,1,workability,2,workshop drawings,1,Workshop repair,1,
ltr
item
Strukts: Changes in ACI318-11
Changes in ACI318-11
https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjgbYlf_tRmBGOkYmFmTTRxLCwCrKWXqAuQzNKK-ncRXSZ_5FsQmPVZzfbkeUnw0PFIYuwYFTnMSWSDYVENWhHNE6HJ6fjGQpihnGPIb7JNiCJx-L1x3lavE7aKQ1rKpEeivyhfzXupfhE/s320/images.jpg
https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjgbYlf_tRmBGOkYmFmTTRxLCwCrKWXqAuQzNKK-ncRXSZ_5FsQmPVZzfbkeUnw0PFIYuwYFTnMSWSDYVENWhHNE6HJ6fjGQpihnGPIb7JNiCJx-L1x3lavE7aKQ1rKpEeivyhfzXupfhE/s72-c/images.jpg
Strukts
https://www.strukts.com/2012/07/changes-in-aci318-11_66.html
https://www.strukts.com/
https://www.strukts.com/
https://www.strukts.com/2012/07/changes-in-aci318-11_66.html
true
7606260228666216043
UTF-8
Loaded All Posts Not found any posts VIEW ALL Readmore Reply Cancel reply Delete By Home PAGES POSTS View All RECOMMENDED FOR YOU LABEL ARCHIVE SEARCH ALL POSTS Not found any post match with your request Back Home Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sun Mon Tue Wed Thu Fri Sat January February March April May June July August September October November December Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec just now 1 minute ago $$1$$ minutes ago 1 hour ago $$1$$ hours ago Yesterday $$1$$ days ago $$1$$ weeks ago more than 5 weeks ago Followers Follow THIS PREMIUM CONTENT IS LOCKED STEP 1: Share to a social network STEP 2: Click the link on your social network Copy All Code Select All Code All codes were copied to your clipboard Can not copy the codes / texts, please press [CTRL]+[C] (or CMD+C with Mac) to copy